The full four-step assembly, from base plates to the finished window or door rail. Read the safety notes before you start.

Important safety warnings

Make sure to install the SHIM-ME as level as possible.

  • Install the number of SHIM-ME units required to support the system.
  • Some assistance may be required.
8"
Max base-plate spacing

Edge to edge

1 1/4"
Lowest height

Wedge fully nested

1 3/4"
Max adjustable height

Before extension

1/16"
Per notch

Height adjustment step

Before you start

What's in the box.

Included

  • Base plateAnchors to the sill pan
  • ScrewsSecure wedge, extension and thermal break
  • Base wedge & adjustable wedgeSets the working height
  • 1/2" extensionOptional, for extra height
  • Thermal breakSits under the rail

Tools recommended

  • Tape measure
  • Power drill with 1/4" drill bit
  • Power drill or Phillips screwdriver
  • Hand level

Not included

  • Wood or concrete anchors
  • Waterproof sealant
  • Sill pan

Application

The SHIM-ME system can be used for both windows and doors. The units must be installed prior to final window or door installation.

Choose the required width

Check your window or door opening for the required width. The SHIM-ME width should fit your sill pan (pan not included). Custom sizes available.

Work out how many you need →

The install

Four steps, in order.

  1. 01

    Installing the base plates

    Locate the sill pan and place it over the location where you intend to install your door or window. Lower it slowly and set it into place, then locate the corner and place the first base plate.

    • 01Place the base plate a couple of inches from the end, flat face facing down.
    • 02Drill the two anchor holes with a power drill and a 1/4" bit.
    • 03Secure the base plate using anchors suited to your application — check your project requirements for the correct type.
    • 04Repeat for the remaining base plates, spacing each set at a maximum of eight inches edge to edge.
    • 05Fully secure all base plates, then apply waterproofing — make sure both the anchors and the base plates are fully sealed.
  2. 02

    Installing the base and adjustable wedge

    The base wedge slides onto the base plate. Set it in front of the plate, match the bottom slots, and slide it into place flush with the base plate.

    • 01Secure the base wedge with the provided screw and tighten fully with a Phillips screwdriver.
    • 02Attach the adjustable wedge by sliding it onto the base wedge, matching the slots.
    • 03Sliding the wedge to fully cover all grooves sets the lowest possible height — about 1 1/4".
    • 04To raise it, pull the adjustable wedge out and slide it to the next notch. Each slot adjusts the height by about 1/16".
    • 05The maximum adjustable height is about 1 3/4". Measure from the top of the shim assembly to the finished floor with a tape measure.
    • 06Once at the required height, secure the adjustable wedge to the base wedge with the provided screw and tighten fully.
  3. 03

    Installing the optional extension and thermal break

    The assembly can be extended for extra height. SHIM-ME includes a half-inch extension for projects that need to go past 1 3/4". If no extension is required, skip to the thermal break.

    • 01To fit the extension, slide it onto the adjustable wedge, matching the notches, and secure it with the provided screw.
    • 02The thermal break installs either to the half-inch extension or directly to the adjustable wedge.
    • 03Slide the bottom notches onto the assembly, ease it into place, and secure it with the provided screw.
    • 04Repeat for the remaining SHIM-ME assemblies as required.
  4. 04

    Installing the window or door rail

    Once every assembly is fully secured and waterproofed, you can fit the rail. Place the bottom window or door rail on top of the SHIM-ME assemblies and lower it slowly into place over the thermal break.

    • 01Secure the rail using the required anchors, inserting them through the rail and into the SHIM-ME assemblies.
    • 02Fully secure the anchors as required.
    • 03Install windows or doors per your project specifications.

Installation complete — enjoy your new SHIM-ME.

Assembly video

Watch it end to end.

Technical support

Stuck on an opening?

Questions about an install, or an opening that doesn't divide evenly? The spec desk will work it out with you.

© SHIM-ME — Installation Manual

This page reproduces the printed manual. Keep the PDF with the job file — it carries the same steps and diagrams for the crew on site.